Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 10:00 am, March 9)



The Company's Official Page
http://www.tepco.co.jp/en/press/corp-com/release/12030903-e.html
Back To Previous Page

Press Releases
Press Release (Mar 09,2012)
Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 10:00 am, March 9)

Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March 
11, 2011, TEPCO's facilities including our nuclear power stations have been 
severely damaged. We deeply apologize for the anxiety and inconvenience 
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on 
April 17, 2011, we have compiled the roadmap towards restoration from the 
accident and on July 19 we accomplished the Step1 target "Radiation dose 
is in steady decline". Then on December 16 we confirmed the accomplishment 
of the Step 2 target "Release of radioactive materials is under control 
and radiation doses are being significantly held down".
In addition, on December 21, 2011, we have compiled the "Mid-to-long-Term 
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power Units 
1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will 
implement Mid-to-Long Term countermeasures towards the decommissioning of 
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to 
their homes as soon as possible and reduce the anxiety of the people in 
Fukushima and the whole nation as soon as possible.

Below is the status of TEPCO's major facilities.

* The updates are underlined.

[Nuclear Power Station] 
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to 
 the earthquake:
 (Units 4 to 6: outage due to regular inspections before the earthquake)

 * With regard to the thermometer placed at the lower part of RPV (top of 
 the lower head 135°) whose trend which showed a different trend while 
 others showed the increasing trend after we decreased the water 
 injection rate to the Unit 2 Reactor from the feed water system on 
 February 22, we reported to Nuclear and Industrial Safety Agency of 
 Ministry of Economy, Trade and Industry on March 1. We will continue 
 monitoring this thermometer.
 · At 5:00 am on March 9, the temperature of the lower part of the RPV 
 (top of the lower head 135°) : approx. 41.8 °C
 · At 5:00 am on March 9, the temperature of the lower part of the RPV 
 (top of the lower head 270°) : approx. 40.3 °C (reference)

 * At 10:00 am on March 9, we started transfer of accumulated water from 
 the underground of Unit 6 turbine building to the temporary tank.

 * On March 8, 2012, we conducted sampling of the air inside the Gas 
 control system of Unit 3 PCV.. As result of the analysis, we confirmed 
 Xenon 135 was below detection limit (9.8x10-2Bq/cm3) at the inlet of 
 the system and also confirmed that it was below 1.0xBq/cm3 which is 
 judgment criteria of recriticality. 

 * At 2:25 pm, on March 8, we started injecting hydrazine into Unit 4 
 spent fuel pool by using circulating cooling system. At 4:10 pm on the 
 same day, we stopped the injection.

· Fukushima Daini Nuclear Power Station: 
 Units 1 to 4: shutdown due to the earthquake

· Kashiwazaki Kariwa Nuclear Power Station:
 Units 6: under normal operation
 (Units 1 to 5 and 7: outage due to regular inspections)

[Thermal Power Station]
· Power supply has returned to normal and the facilities damaged by the 
 earthquake are now being handled in a timely manner.

[Hydro Power Station]
· Power supply has returned to normal and the facilities damaged by the 
 earthquake are now being handled in a timely manner.

[Impacts on Transmission Facilities]
· Power supply has returned to normal and the facilities damaged by the 
 earthquake are now being handled in a timely manner.

[Impacts on Power Supply and Demand Balance]
We expect to maintain stable power supply in March.
Daily supply and demand balance is announced at our "TEPCO Electricity 
Forecast".

Appendix: Past Progress (As of 10:00 am on March 9, 2012) (PDF 470KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)

* Revised past progress





Related Latest News
"Tokyo Electric Power Company, Inc." more
"Electric Power & Gas" Listed Companies more
"Electric Power & Gas" Non-listed Companies more
"Tokyo" Companies more

WARNING: (1) Because this website uses a computer program to automatically collect and display press-release text information, errors or inaccuracy may occur. Double-check with information on these companies' official websites. (2) A press release may contain facts, figures and preliminary forward-looking statements which are subject to change.
Latest Press Release Search


Fukushima | power supply | cloud | solar
*NOTE: Recommended keywords shown above.
Your Most Recently Viewed Companies
Visit any of the company pages in JPubb, and your most recently viewed companies will automatically show up here.