Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of June 21)
Press Releases
|
|
Press Release (Jun 21,2012)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of June 21) |
|
We are announcing the status of major inspections and restoration works and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/ Restoration Status
◇ Inspection and restoration completed between June 15 to June 21, 2012
(Completed on the following date)
- No notable activity during this week.
◇ Inspection and restoration to be commenced between June 22 to June 28, 2012
(To be commenced on the following date)
- No notable activity during this week.
◇ Work Schedule of Major Inspection and Restoration from June 17 to July 14, 2012
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) ...Appendix
Appendix::
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) (PDF 14.1KB)
|
|
|
|
|
|
|
Related Latest News
"Tokyo Electric Power Company, Inc."
more
"Electric Power & Gas" Listed Companies
more
"Tokyo" Companies
more
WARNING: (1) Because this website uses a computer program to automatically collect and display press-release text information, errors or inaccuracy may occur. Double-check with information on these companies' official websites. (2) A press release may contain facts, figures and preliminary forward-looking statements which are subject to change.